Overview

Austin Water has designed improvements to the Guildford Cove Pump Station. Through the Guildford Cove Pump Station Improvements Project, we will install two new tanks to expand capacity and redundancy; replace and refurbish equipment; and replace valve vaults on Maury’s Trail and Bell Mountain.

One contractor is handling this project along with the Glenlake Pump Station Bypass Improvements Project and the Lookout Lane Pump Station Improvements Project.

For projects like this, Austin Water partners with the City’s Capital Delivery Services (CDS), and their project management staff will oversee construction.

Timeline

The contractor will be working over a two-year period, but not on all three projects consistently during that time. Construction on the Guildford Cove portion of the project began in November of 2024 and the work is estimated to take nine to ten months to complete.

Communications

Sign up for Updates!

Contacts

Josh Oeffinger, Project Manager
Capital Delivery Services, City of Austin
(512) 974-7115
josh.oeffinger@austintexas.gov

 

Leo Garcia, Construction Inspector
Capital Delivery Services, City of Austin
(512) 663-4681
leo.garcia@austintexas.gov 

 

Cynthia Miller, JD
Public Information Office, City of Austin
(512) 972-0268
cynthia.miller@austintexas.gov