Construction is Underway
The below map is posted at various points throughout the park while construction is in progress.
Project Description
The Parks and Recreation Department (PARD) has worked closely with the Watershed Protection Department, (WPD), Public Works Department, (PWD), and the Austin Water utility, (AWU) to provide a permanent solution to stabilize the channel embankments, arrest the erosion and replace the lost infrastructure to restore connectivity through the park. While the long-term solution was being developed, smaller interim projects were completed to temporarily protect existing parkland, infrastructure, and private property upstream. These temporary measures included using large boulders for armoring areas severely scoured by erosive forces at two separate locations along the channel. Another small project removed and stored an existing metal-truss pedestrian bridge that was vulnerable to loss along the heavily scoured cut-bank of the channel just east of Krieg Softball Fields #10 and #11.
During construction, public access crossing the creek within the project limits will not be permitted for the safety of the public and the contractor.
Additional information on the channel stabilization project can be found at the Watershed Protection Department channel stabilization
Aerial photo of site under construction
Pedestrian Bridge delivery
Concrete drop structure
Project Update
Construction is around 90% complete. The pedestrian bridge has been delivered to the site and is anticipated to be installed near the end of 2024. Note: Construction work will be taking place on Saturdays between 8am and 7 pm as well as Monday through Friday from 7am to 7pm.
Anticipated Schedule
- Fall 2017-Spring 2020: Preliminary Design (Complete)
- Summer 2020: 60% Design Complete (Complete)
- Fall 2021: 100% Design Complete (Complete)
- Spring 2022: Issued for Bid (Complete)
- Summer 2022: Construction Start (August 22, 2022, ongoing)
- Late Fall/Winter 2024: Pedestrian Bridge installation
- Early 2025: Construction End
Please note that as in any construction project, schedules are projected as accurately as possible. All dates are subject to change due to the nature of construction and the weather.
Community Engagement
5/3/2017 Design Commission Review
6/17/2017 Austin Ridge Riders Meeting
Funding and Resources
The estimated construction cost for the bridge and stabilization project was 25 million dollars funded through a combination of Drainage Utility Funds, General Funds, 2018 Bond Funds, and a FEMA Hazard Mitigation Grant.
Contact Information
D'Anne Williams, PARD Project Manager, 512-974-9456
Darryl Haba, PW Project Manager, 512-974-2777