The concept plan for Highland Neighborhood Park was completed in 2017 through input from community members and provides a vision for future development. Phase 1 of implementation was completed in 2019 and included the installation of a new playground. Phase 2 of implementation began with community input to further the park design and prioritize the improvements for the next phase. As of July 2024, Phase 2 is complete and open to the public. Construction on the bridge began in January 2025. City Council District 4

Background 

Bridge Project Description January 2025

Highland Neighborhood Park will soon have a new bridge for improved pedestrian connectivity.  The work includes demolition of a portion of the new sidewalk to make an ADA connection, installation of bridge abutments, and the delivery and installation of a new bridge connecting the existing sidewalk to the natural surface trail across the Waller Creek tributary. The construction site will be revegated upon completion. The loop trail at Highland Park will be temporarily closed during construction.

 

Anticipated Timeline

January 2025: Project Kickoff
February 2025: Abutment construction and bridge delivery
March 2025: Concrete walkway connection, Project Completion

Funding and Resources

The project is funded by Austin Parks Foundation through an ACL Music Festival Community Impact Grant applied for by the Highland Neighborhood Association.

Contact Information

For more information or project questions, contact Patrick Beyer, Project Manager, Parks and Recreation Department by phone at (512) 974-9476 or by email.

Previous Improvement Projects

Concept Planning Process and Phase 1 Implementation

Project Description

The scope for phase 2 of the concept plan implementation included: two 125’ ball fields with lighting, a new site irrigation system, a loop walking trail, benches, a new drinking fountain, parking lot improvements, utilities for a future restroom/community building and 25 additional trees. The design reflects sensitivity for the Waller Creek watershed and provides green infrastructure opportunities in collaboration with Austin’s Watershed Protection Department. The project also participated in the City of Austin Arts in Public Places (AIPP) program to commission a permanent art installation within the park.

Concept plan for Phase 2

Project Timeline

  • April 2021: Community Engagement (Complete)
  • Summer 2021: Permitting and Construction Documents (Complete)
  • Fall 2022: Construction Started
  • Summer 2024: Construction Completion

Community Engagement

PARD held two virtual meetings in 2021. The purpose of the meetings was to develop the design of the concept plan further and to prioritize the scope of phase 2. A summary of the two community meetings can be found below.

Virtual Community Meeting #1
March 31, 2021
Virtual Community Meeting #2
June 24, 2021

Community Survey: March 31 to April 25, 2021 (view summary of results)

Community members identified preferences between variations of park designs.

Funding and Resources

This project construction is funded through the 2018 GO Bond and Parkland Dedication funding.  Additionally, an Urban Forestry Grant through the City of Austin Development Services was awarded for the planting of 25 additional trees. The Highland Park Neighborhood Association has also applied for an Austin Parks Foundation grant for additional funding.

Contact Information

For more information or project questions, contact Patrick Beyer, Project Manager, Parks and Recreation Department by phone at (512) 974-9476 or by email.

People gather to listen to a speaker at the ribbon cutting.