During the 2015 Memorial Day rain event and flooding, the concrete bridge at Country Club Creek sustained major structural damage and collapsed when the concrete footings supporting the bridge sections were undermined by flood waters surging downstream through the channel. Severe erosion occurred all along the drainage channel. The Parks Department has worked closely with the Watershed Protection Department to provide a permanent solution to stabilizing the channel and replacing the bridge crossing of the creek. Work on site began in late September 2022 and is now complete and open to the public! A ribbon cutting will be held on February 6th at 9:30am on the Krieg Fields side of the park, 515 S. Pleasant Valley Rd.  City Council District 3

Update

A ribbon cutting celebration will be held on February 6th at 9:30am on the Krieg Fields side of the park and bridge entrance. Please join us to celebrate the engineering, design and construction of this stabilization project that protects parkland from further erosion and provides access through and to Roy G. Guerrero Park. 

photo and text for ribbon cutting eventmap of the location of the event

 

 

view of new bridge installation looking south

 

Project Description

Austin Parks and Recreation (APR) has worked closely with the Watershed Protection Department, (WPD), Capital Delivery Services (CDS), and the Austin Water utility, (AWU) to provide a permanent solution to stabilize the channel embankments, arrest the erosion and replace the lost infrastructure to restore connectivity through the park. While the long-term solution was being developed, smaller interim projects were completed to temporarily protect existing parkland, infrastructure, and private property upstream. These temporary measures included using large boulders for armoring areas severely scoured by erosive forces at two separate locations along the channel. Another small project removed and stored an existing metal-truss pedestrian bridge that was vulnerable to loss along the heavily scoured cut-bank of the channel just east of Krieg Softball Fields #10 and #11.

Additional information on the channel stabilization project can be found at the Watershed Protection Department channel stabilization.

creek channel looking towards Colorado River

Channel grading September 2025

Project Timeline

  • Fall 2017-Spring 2020: Preliminary Design
  • Summer 2020: 60% Design Complete
  • Fall 2021: 100% Design Complete
  • Spring 2022: Issued for Bid
  • Summer 2022: Construction Start
  • Late Fall/Winter 2024: Pedestrian Bridge installation
  • September 2025: Construction complete and open to the public 
  • February 6th, 2026: Ribbon cutting celebration                

Community Engagement

5/3/2017         Design Commission Review

6/17/2017       Austin Ridge Riders Meeting

Funding and Resources

The estimated construction cost for the bridge and stabilization project was 25 million dollars funded through a combination of Drainage Utility Funds, General Funds, 2018 Bond Funds, and a FEMA Hazard Mitigation Grant.

Contact Information

D'Anne Williams, APR Project Manager, 512-974-9456

Darryl Haba, CDS Project Manager, 512-974-2777