Waller Creek Flood Management and Water Quality Improvements Study

CIP 485-617-5011


Summary

This study will develop a flood management plan for the lower Waller Creek watershed (W. 15th to Town Lake). Also, a water quality master plan for the entire Waller Creek watershed is to be prepared. Architectural review of the proposed improvements will be performed to ensure compatibility.

Status

On March 9, the City Council approved Loomis and Associates as the engineering consultant. The Draft Report was completed in November, 1995; the Final Report is due in January 1996.

Description

The details developed by the study will include the costs and economic benefits of the flood management and water quality plan. Evaluation of the plan will indicate the required funding for a future bond election or appropriation.

Basic Data

  • Project Contact: David G. Gerard, Department of Public Works and Transportation, 499-7022
  • Project Manager: Gary Kosut, Department of Public Works and Transportation, 499-7214
  • Amount Appropriated: $180,000
  • Estimated Completion Date: November, 1995

    Revised January 9, 1996

    Back to the January 1996 Contents
    To Downtown Map

  • Official Seal of the City of Austin
    Austin City Connection - The Official Web site of the City of Austin
    Contact Us: Send Email or 512-974-6415.
    Legal Notices | Privacy Statement
    © 1995 City of Austin, Texas. All Rights Reserved.
    P.O. Box 1088, Austin, TX 78767 (512) 974-2000