Street Reconstruction, Overlay and Utility Improvements
Congress Avenue, Brazos, Colorado, and San Jacinto Streets
Summary
The project will provide for the reconstruction, pavement overlay, and
water and wastewater improvements of various downtown streets.
Status
- Congress Avenue: Construction is complete.
- San Jacinto Street: The design is complete; construction is scheduled for spring 1997
- Lavaca Street: Construction is to start mid-September and is expected to take 6 months to complete.
Issues
Colorado and Brazos will be bid following completion of Capital Metro's
bus route plan.
Description
Planned improvements include repair of pavement failures, construction
of concrete bus pads, construction of sidewalk ramps, and overlay and
striping of the streets, in addition to replacement of old and/or
shallow
water and wastewater lines. Construction limits for each of the streets
are:
- San Jacinto Street: 6th - 9th
- Lavaca: 11th - MLK
Basic Data
Project Manager: Sondra Creighton, P.E., Department of Public Works
and Transportation, 440-8444
| Construction
Estimate | Predominant Funding
Source |
| San Jacinto Street | $400,000 | C.I.P. |
| Lavaca Street | $1,444,452 | C.M.T.A. |
Revised August 28, 1996