Shoal Creek Flood Repairs
Summary
This phase of the project is a gabion wall failure near West Avenue and Shoal Creek.
Status
Final construction plans and specifications are being developed.
Description
The failed gabion section will be removed and replaced with approximately 150 lineal feet of concrete wall. Approximately 150 feet of sidewalk will also be installed connecting a hike-and-bike trail from the east end of the Energy Management Building, southeasterly to the existing sidewalk.
Basic Data
Project Contact: Stuart Strong, Parks and Recreation Department, 499-6766
Project Manager: Ginger Daniels, P.E., Department of Public Works and Transportation, 499-0145
Construction Start Date: September 1995
Completion Date: January 1996
Estimated Cost: $350,000
Revised Nov. 7, 1995