Shoal Creek Flood Repairs
Summary
This phase of the project is a gabion wall failure near West Avenue and Shoal Creek.
Status
The project is substantially complete.
Description
The failed gabion section will be removed and replaced with approximately 150 lineal feet of gabion wall. Approximately 150 feet of sidewalk will also be installed with handrails connecting a hike-and-bike trail from the east end of the Energy Management Building, southeasterly to the existing sidewalk.
Basic Data
Project Manager: Walter Boettcher, P.E., Department of Public Works
and Transportation, 499-7220
Construction Start Date: September 1995
Completion Date: June 1996
Estimated Cost: $350,000
Revised August 28, 1996
Back to the September 1996
Contents
|