South 1st Street
Summary
This project will widen S. 1st Street from Riverside Drive to 500' south of Barton Springs Road. Originally these improvements were included in the S. 1st St. Bridge project (TxDOT). The roadway improvements (upgrade from 4 to 6 lanes with intersection improvements) will now be bid as a City project. This project will improve traffic flow and safety.
Status
The design is complete. At the request of the Barton Springs Merchants Association, advertisement has been delayed until construction of Barton Springs Road / S. Lamar Blvd. intersection is complete. Recent requests for redesign of water facilities have been completed. Planning approval of the revisions and preparation of the project manual are complete. Bids were opened on July 27, 1995, and the apparent low bidder was BRH-Garver. The project was awarded by the City Council on September 14, 1995, and construction started on October 28, 1995.
Basic Data
Project Contact: David G. Gerard, Department of Public Works and Transportation, 499-7022
Project Manager: Tom Hansell, DPWT, 505-5603
Design Consultant: Joe Walther
Bid Date: July 27, 1995
Contract Award Date: September 14, 1995
Construction Estimate: $1,446,000
Construction Start Date: October 28, 1995
Estimated Completion Date: September, 1996
Revised Nov. 7, 1995