South 1st Street


Summary

This project will widen S. 1st Street from Riverside Drive to 500' south of Barton Springs Road. Originally these improvements were included in the S. 1st St. Bridge project (TxDOT). The roadway improvements (upgrade from 4 to 6 lanes with intersection improvements) will now be bid as a City project. This project will improve traffic flow and safety.

Status

The project will be constructed in five phases. Phase I has been completed, and Phase II started December 14, 1995. The total project should be completed by July 1996.

Basic Data

  • Project Contact: David G. Gerard, Department of Public Works and Transportation, 499-7022
  • Project Manager: Tom Hansell, DPWT, 505-5603
  • Design Consultant: Joe Walther
  • Bid Date: July 27, 1995
  • Contract Award Date: September 14, 1995
  • Construction Estimate: $1,446,000
  • Construction Start Date: October 28, 1995
  • Estimated Completion Date: September, 1996

    Revised Jan. 9, 1996

    Back to the January 1996 Contents
    To Downtown Map

  • Official Seal of the City of Austin
    Austin City Connection - The Official Web site of the City of Austin
    Contact Us: Send Email or 512-974-6415.
    Legal Notices | Privacy Statement
    © 1995 City of Austin, Texas. All Rights Reserved.
    P.O. Box 1088, Austin, TX 78767 (512) 974-2000